Tungsten Mining Advances $1.57 Billion Watershed Tungsten Project Towards Final Investment Decision
Australian-listed Tungsten Mining has completed a definitive feasibility study (DFS) for its Watershed tungsten project in Far North Queensland, outlining a pre-tax net present value (NPV) of A$1.57 billion and an internal rate of return (IRR) of 70%.
The study forecasts a post-tax NPV of A$1.11 billion and a post-tax IRR of 57%, with pre-tax capital payback expected within 18 months of first revenue.
Located approximately 115 kilometres northwest of Cairns, the project is targeting first production in June 2027, subject to a final investment decision (FID) expected in December 2026.

Tungsten Mining chairman Gary Lyons described completion of the feasibility study as a major milestone, saying it provides a foundation for advancing the project towards development.
The DFS established a probable ore reserve of 36.6 million tonnes grading 0.124% tungsten trioxide (WO₃), containing approximately 45,500 tonnes of WO₃.
Watershed is expected to produce 31,279 tonnes of tungsten trioxide over a 13.1-year processing life, with average annual production of approximately 2,700 tonnes during steady-state operations.
Project economics and capital requirements
The feasibility study estimates remaining pre-production capital expenditure at A$206.6 million, with life-of-mine C1 cash costs of US$440 per metric tonne unit (mtu).
The base-case economic assessment uses an average ammonium paratungstate (APT) price of US$1,500 per mtu. At an illustrative spot price of US$2,675 per mtu, the project’s pre-tax NPV increases to A$4.12 billion.
The project secured its principal mining and environmental approvals in September, allowing early development activities to proceed. Metallurgical testing has also confirmed that Watershed can produce saleable tungsten concentrate.
Tungsten Mining has committed A$57.8 million towards early works and procurement, while the remaining funding requirement is estimated at approximately A$255 million.
Financing and offtake negotiations underway
The company has received non-binding debt proposals supporting potential project gearing of up to 70%. It is also negotiating with prospective offtake partners in Asia, Europe and North America.
Lyons said the company’s immediate priority is to finalise binding offtake and non-equity financing arrangements to support the final investment decision and maintain progress towards first production in mid-2027.
With approvals secured, early works underway and long-lead procurement progressing, Tungsten Mining is preparing to move Watershed into full-scale construction once the investment decision is made.